Project DescriptionH&R Construction was awarded this publicly bid project as the General Contractor. The project consisted of multiple additions and renovations throughout the Spirit Lake Schools Campus. This included new cafeterias and commons areas at the high school and middle school, a new gym lobby added onto the existing competition gym, a new weight room addition, remodeled locker rooms, and upgrades to the existing old gym mechanical systems. These additions and renovations totaled nearly 65,000 sq. ft.
This project required extensive phasing and coordination with all parties to achieve desired completion dates. The project started in April 2013 and had phases being complete as early as August 2013, with the final phase being completed in November of 2013. Project DetailsContract Type: General Contractor - Competitively Bid
Project Type: Addition and Renovation Size: 65,000 Sq. Ft. Client Reference : Spirit Lake Community Schools - Mr. David Dau |